All News

As part of our ongoing mission to provide safe, reliable electricity to our members, we have contracted to have mechanical cleaning done on 4 feeder lines in our service territory.  This work will begin in January and may take up to 6 months to complete.  As such, members who have recently or will soon receive a letter may not see crews in their immediate neighborhood for some time. Later in the year, we will update you with other areas of work to be completed. You may view our right-of-way policy at https://www.ieca.coop/right-way-maintenancefield-work.

Houston Feeders 2 & 7 contracted to Asplundh

Darien Feeder 1 contracted to Kiowa Line Builders

Edgar Springs Feeder 6 will be a full year project by IECA ROW crew.

If you have any questions please feel free to contact the office at 866-621-3679.

Additional Resources:

Attachments